Repair works on the Lefkoşa-İskele road began on the weekend. During the works, damaged parts of the section of the road between Ercan cloverleaf junction and İskele will be repaired.
The works are expected to last for 2 months in case weather conditions are suitable for laying asphalt. Dring the works a total of 5,700 tons of asphalt will be used to patch a total area of 41 thousand meter square road. The works will also include drawing of the road lines and will cost a total of 2.4 million TL.